Standard Operating Procedure Flame Photometer
SCOPE/PURPOSE:
To ensure correct method of operation for Flame Photometer.
RESPONSIBILITY:
Testing Executive/ Chemists
ACCOUNTABILITY:
Lab Manager
PROCEDURE:
General (PNEUMATICS)
- Ensure that the Air-Tube, Gas-Tube and the Drain Tube are properly connected.
- Switch on the Compressor, Ensure that the output pressure is closed to 0.50kg/cm2.
- Dip the atomizer capillary tube in distilled water & ensure to regulate the drops.
- Open the FUEL GAS FINE ADJ Valve & adjusted the flame by half turn.
- Switch on the fuel supply.
General (Electronics)
- Switch on the FPM Unit 128
- Wait for ready
- Click LOGIN / ENTER
- REPORT:-One can view ALL REPORTS. Exit: - From UTM SET SPEED: - only used machine have variable speed
General (Menu)
- Press Menu Key from system.
- Delete all previous setup with Press 1 & 2.
- Edit Date & time Set Flame as per requirement.
- Set average time by CLR
- Set up backup data & concentration as per requirement
- Started calibration & then sample as per instrument interaction.